How to Measure for Concrete (and Not Run Short)

Running out halfway through a pour is the expensive mistake. Measure inside the forms, convert everything to feet, split odd shapes into simple ones, and add a waste allowance. Here's the method with worked examples.

The one formula

Cubic yards = length (ft) × width (ft) × thickness (ft) ÷ 27

Concrete is sold by the cubic yard, which is 27 cubic feet. Bags are sold by what they yield: an 80 lb bag of standard mix makes about 0.60 ft³ (QUIKRETE), so a cubic yard is 45 bags.

Measure in the right places

Example: readings of 3.5, 4, 4.5, 5 and 4 in average out to 4.2 in. Using 4 in would leave you about 5% short.

Inches to feet

Divide inches by 12, or use this table:

InchesFeet
1 in0.083 ft
2 in0.167 ft
3 in0.250 ft
4 in0.333 ft
5 in0.417 ft
6 in0.500 ft
7 in0.583 ft
8 in0.667 ft
9 in0.750 ft
10 in0.833 ft
11 in0.917 ft

So 10 ft 6 in is 10.5 ft, and a 4 in slab is 0.333 ft thick. pourplot's calculator takes feet and inches directly, so you can skip this step.

Odd shapes

How much extra to add

Some concrete is always lost to spillage, form bulges, uneven subgrade and what's left in the mixer. pourplot adds 10% by default. Raise it if the ground is rough or you're pouring by hand. Lower it only for small, carefully formed pours. Ordering a little over is much cheaper than a second delivery or a cold joint where a short pour stopped.

A quick checklist

  1. Sketch the pour and split it into rectangles, circles and steps.
  2. Measure inside the forms; average the thickness.
  3. Convert to feet (or let the calculator do it).
  4. Add the pieces and the waste allowance.
  5. Turn cubic yards into bags or a ready-mix order, and print the ticket.

Sources

Estimates for planning. Follow your plans, your supplier's instructions and your local building code.